Skip to main content
Generalmarkus41

delivery-tracker

Generate milestone tracking configurations and progress report templates for fixed-scope engagements. Use when setting up project delivery tracking at engagement kickoff or when a client needs a status update format.

Stars
12
Source
markus41/claude
Updated
2026-05-11
Slug
markus41--claude--delivery-tracker
View on GitHubRaw SKILL.md

// install — copy + paste into any project

mkdir -p .claude/skills && curl -fsSL https://raw.githubusercontent.com/markus41/claude/HEAD/plugins/lobbi-engagement-toolkit/skills/delivery-tracker/SKILL.md -o .claude/skills/delivery-tracker.md

Drops the SKILL.md into .claude/skills/delivery-tracker.md. Works with Claude Code, Cursor, and any agent that loads SKILL.md files from .claude/skills/.

Delivery Tracker

Generate a milestone tracking structure and weekly status report template for a fixed-scope Lobbi engagement. Establishes delivery cadence, client visibility, and escalation triggers from day one.

Standard Lobbi Engagement Phases

Every fixed-scope engagement follows these phases. Adjust durations based on project complexity.

Phase # Name Standard Duration Key Output
1 Kickoff 1 week Kickoff meeting, system access confirmed, project plan finalized
2 Discovery and Design 1–2 weeks Workflow design document, integration specs, client approval
3 Build Sprint 1 2–3 weeks Core automation built, internal testing complete
4 Build Sprint 2 1–2 weeks (if needed) Integrations complete, exception handling, end-to-end testing
5 User Acceptance Testing 1–2 weeks UAT environment delivered, client tests and approves
6 Go-Live 1 week Production deployment, smoke testing, go-live confirmation
7 Hypercare 1–2 weeks Monitoring, issue resolution, transition to steady state

Milestone Tracker Template

For each milestone in the engagement, document:

# Milestone Phase Deliverables Acceptance Criteria Client Dependencies Target Date Status Health
1 Kickoff complete Kickoff Kickoff meeting held; project plan shared; system access received PM confirms all access credentials received and tested; project plan distributed Client provides system credentials within 3 business days of contract signing [Date] Not Started
2 Design approved Discovery/Design Workflow design document; integration spec; data mapping Client signs off on design document Client subject matter expert available for 2 design sessions [Date] Not Started
3 Build Sprint 1 complete Build Core automation functional in dev environment; Lobbi internal QA passed Lobbi QA checklist complete; PM demo to client (informational, not sign-off) None [Date] Not Started
4 Build Sprint 2 complete Build All integrations functional; exception handling complete; end-to-end test passed End-to-end test log reviewed and approved by Lobbi PM None [Date] Not Started
5 UAT complete UAT UAT environment available to client; UAT test script provided Client executes test script; all critical test cases pass; client signs UAT sign-off sheet Client designates UAT testers; client commits [N] business days to UAT [Date] Not Started
6 Go-live Go-Live Production deployment complete; smoke test passed; client operations team confirmed ready Smoke test passed; client confirms production transactions processing correctly Client confirms go-live date; client business team available on go-live day [Date] Not Started
7 Hypercare complete Hypercare Hypercare period ended; known issues resolved or documented; runbook delivered Zero critical open issues; client confirms readiness to operate independently Client reports issues within 4 business hours during hypercare [Date] Not Started

Status values: Not Started | In Progress | Complete | Blocked | At Risk

Health RAG:

  • Green: On track; no issues
  • Amber: Minor risk or delay; recoverable without timeline change
  • Red: Significant risk; timeline impact likely or already occurring

Client Dependency Register

Track all items Lobbi needs from the client to proceed. Delays in these items extend the project timeline day-for-day.

# Dependency Needed By Needed For Requested Date Received Date Status Days Delayed
1 System credentials: [System] [Date] Build Sprint 1 start [Date] Pending
2 Subject matter expert: design sessions [Date] Design phase [Date] Pending
3 UAT testers designated [Date] UAT phase [Date] Pending
4 Go-live date confirmation [Date] Go-live planning [Date] Pending

Weekly Status Report Template

Send every Friday by 3:00 PM to the client point of contact and copy the Lobbi account lead.


[Project Name] — Weekly Status Report Week of: [Monday date] – [Friday date] Report #: [N] Prepared by: [PM Name]


Project Health

Overall [Green / Amber / Red]
Schedule [Green / Amber / Red]
Scope [Green / Amber / Red]
Client Dependencies [Green / Amber / Red]

This Week — Completed

  • [Specific accomplishment with outcome, not just activity]
  • [e.g., "Completed integration between Applied EPIC and email platform — tested with 50 sample policy records, all passing"]
  • [e.g., "Resolved exception handling for out-of-state policies — routing to manual review queue as designed"]

Next Week — Planned

  • [What Lobbi will do next week]
  • [Be specific enough that the client knows what to expect]

Milestone Status

Milestone Target Date Status Health Notes
[Milestone] [Date] [Status] [RAG] [If Amber/Red: brief explanation]

Open Decisions Needed

Items the client must decide this week for work to proceed:

# Decision Required Context Decision Needed By Owner
1 [Decision] [Why it's needed] [Date] [Client contact]

If no decisions are currently needed, write: No client decisions required this week.


Risks and Blockers

# Risk / Blocker Impact Mitigation Owner Status
1 [Risk description] [Timeline / scope / budget] [What Lobbi is doing about it] [Owner] Active / Resolved

If no risks or blockers, write: No open risks or blockers.


Pending Client Dependencies

Dependency Needed By Status
[Item] [Date] Received / Pending — [N] days outstanding

Next report: [following Friday date] Questions or concerns? Reply to this email or schedule time: [calendar link]


Escalation Trigger Conditions

The following conditions require escalation beyond the standard weekly status report cadence. Escalate within 24 hours by phone (not email only).

Trigger Escalation Action
Client dependency overdue by 3+ business days Direct call to client sponsor + written notification of timeline impact
Critical blocker with no clear resolution path Immediate call to client; engage account lead
Any milestone slipping by 5+ business days Client call + revised project plan within 3 business days
Scope change request received Follow change order process (see change-order-guard skill)
Client satisfaction concern raised by any team member Account lead involved within 24 hours
Any security or data incident Immediate notification per incident response protocol

Kickoff Checklist

Use at project kickoff to ensure tracking infrastructure is in place before build begins.

  • Milestone tracker shared with client and internal team
  • Weekly status report cadence confirmed with client POC
  • Client dependency register populated with all known items
  • Client escalation contact (name + direct phone) confirmed
  • Lobbi PM added to client communication channels (Slack, Teams, email)
  • Project folder structure created (shared with client)
  • First weekly status report scheduled for end of Week 1